Running web projects in Botswana around safari seasons, public holidays and patchy links

← Blog
Guide • Delivery

Running web projects in Botswana around safari seasons, public holidays and patchy links

A booking site for a Kasane lodge, a staff portal front-end for a Gaborone financial firm and a brochure site for a Francistown supplier share one rhythm underneath. This guide describes a repeatable path from brief to launch and the local calendar facts that move deadlines.

One path for every job

Run each project through the same stages: brief, structure, design, build, content, launch. When a colleague takes over in week five, they should recognise the shape immediately.

Use “waiting on client” as a visible status. It separates delays that are yours from delays that are theirs, which is useful the day someone asks why a launch slipped.

From brief to launch in six steps

  1. Agree scope, and name one owner on your side and one decision-maker on theirs. In a lodge group or a public body, the person who answers email and the person who approves are often different people.
  2. Cut the work into pieces that can be approved separately: structure, designs, a staging build, loaded content, the finished site.
  3. Give every milestone a date and every deliverable a named person.
  4. Get each piece approved before starting whatever depends on it.
  5. Go through a launch checklist: forms, redirects, analytics, SSL and where the domain points.
  6. Write two lines on which parts overran their hours and why.

Plan for the safari calendar

For tourism clients the year has a shape. The dry season, roughly May to October, is when most enquiries arrive, so a booking page, rate sheet or gallery that is still “nearly done” in April costs the lodge real business. Work backwards from the start of high season, not from the date you would like to finish.

The green season from about November is when lodges have time to review copy and photography. Use it for redesigns and content updates, and tell clients early that this is when you can give them your best attention.

Public holidays and the long year-end

  • Sir Seretse Khama Day on 1 July and President’s Day in the third week of July leave a thin month for approvals at government-linked clients.
  • Botswana Day on 30 September and 1 October often becomes a long weekend that decision-makers use to travel.
  • The December shutdown at many firms runs from Christmas well into the first week of January. Secure large approvals before it or plan a January start.
  • Government bodies work to a financial year that starts on 1 April, so budgets and sign-offs tend to bunch up in March and April.

Working with remote clients and slow links

A camp manager in the Okavango may read email once a day over a satellite link. Do not send a 60 MB design file and expect a reply by afternoon. Send a short summary with a link, state the exact decision you need and give a date.

Record the answer against the deliverable the moment it arrives. Voice notes and calls are fine as conversation, but the project needs the verdict written down with a name and a date.

Delays that come up repeatedly

Common causes and what to do about them

What happensWhat helps
Photography arrives lateMake content hand-over a dated milestone at kickoff, not an afterthought
Approval is vagueAsk for a decision by a stated date, with no more than three questions
Two people own one itemName one owner, even if two people contribute
Requests creep past the briefLog each one as an extra and decide whether it is in or out

Hand over properly

Decide before launch what the client receives on the last day: logins, a short walkthrough, domain and hosting details and a plain statement of what ongoing support covers. A one-page handover followed by a check-in two weeks later is often how a finished project turns into a retainer.