Delivering client websites in Uganda, from the first brief to go-live
A site for a Jinja tour operator and a donor-facing site for a Kampala NGO look nothing alike, yet the delivery path is the same. This guide lays out one repeatable route from brief to go-live and points at the places where Ugandan projects usually lose a week.
Use the same milestones every time
Brief, sitemap, design, build, content, launch. When every project follows those stages, anyone on the team can pick up a project they have never touched, which matters when a developer is out for a week.
The most useful status is “with the client for review”. It shows at once whether a delay sits on your side or theirs.
From brief to go-live in six steps
- Confirm scope, one owner on your side and one decision-maker on theirs. For an NGO this is often a programme manager plus a communications officer; name both.
- Break the work into deliverables a client can approve: sitemap, designs, staging build, content loaded, final site.
- Give each milestone a due date and each deliverable one owner.
- Send a deliverable for approval before starting whatever depends on it.
- Run a launch checklist: forms, redirects, analytics, SSL and the domain pointing correctly.
- Close with a short note on what went over hours and why.
Record approvals against the deliverable
Many Ugandan clients approve over WhatsApp or a phone call. That is fine, as long as you note the date and the person against the deliverable afterwards. When a board member in week ten asks who agreed the homepage, you can answer in one line.
It also protects scope. A change after approval is new work, and you can quote it on its own instead of absorbing it.
Plan around the local calendar
- The financial year runs July to June, so NGO and government-linked clients often rush spending and reports in the last quarter and restart slowly in July.
- Public holidays such as Labour Day on 1 May, Heroes’ Day on 9 June and Independence Day on 9 October fall on fixed dates; check them before promising a delivery.
- Christmas through the first weeks of January is slow for decisions, so aim to land approvals before mid-December.
- Connectivity and power can interrupt remote work, so keep staging links and files reachable from more than one place.
Hand over properly
Agree at kickoff what the client receives at handover: logins, a short walkthrough, domain and hosting details and a list of what an ongoing retainer covers. A studio in Mbarara might sit with a school’s admin team for an hour at launch and book a check-in two weeks later.
Small habits like that turn a finished project into a retainer conversation rather than a surprise invoice.
Where projects lose a week
- Waiting for content: set a date for text and photos at kickoff and make it a milestone.
- Late feedback: send approvals with a deadline and short questions, not an open invitation to comment.
- Unclear ownership: one owner per deliverable, even when two people help.
- Scope that keeps moving: log requests as change requests and decide which milestone they belong to.