From signed quote to live site: running client web projects in Zambia
A safari lodge near Livingstone wants bookings before the dry-season peak. A Kitwe supplier wants a catalogue site that procurement can read. A Lusaka NGO needs a donor-facing page by a funder’s deadline. The briefs differ; the way a project can go wrong does not. This is a delivery routine you can reuse for all three.
Work backwards from the client’s fixed date
Zambian clients often have a date they cannot move: a tourist season, a school term, a tender window or a donor report. Ask for that date in the first meeting and plan back from it, leaving a week at the end for the things that always happen.
If the date is unrealistic, say so on day one with a reduced scope that does fit. Telling a client in week six is far more expensive.
Six handovers, each with an owner
- Brief: one person on your side and one decision-maker on theirs, both named in writing.
- Structure: sitemap and page list approved before any design starts.
- Design: one round of consolidated feedback, collected by the client rather than by five managers separately.
- Build: staging link shared and content deadline confirmed.
- Content: client text and photographs loaded and checked page by page.
- Launch: domain pointing, SSL, forms, redirects and a check on a mobile browser.
The business calendar to plan around
- The business and government year follows the calendar year, so budgets open in January and many clients try to finish spending and close reports in November and December.
- January is slow for decisions; do not schedule a first review the week offices reopen.
- Heroes’ Day and Unity Day in early July and Farmers’ Day in early August create short weeks; Independence Day falls on 24 October. Check the exact dates each year.
- Farming and agri-business clients are busiest around planting and harvest, so book their review calls outside those peaks.
- Power cuts and load-shedding happen; agree a rule for what counts as a delay and keep staging links reachable from more than one connection.
Decision-makers who are not in the room
In many Zambian organisations the person briefing you needs a director, a board member or a head-office approval. Ask early who that is and plan a review slot for them.
Record each approval on the deliverable with the date and the name. If a head-office manager asks in week nine why the homepage looks as it does, the answer is one click away.
The three places a week goes missing
- Content that arrives late: make the delivery date for text and photos a dated milestone with a named person.
- Feedback by voice note: ask for a short written summary, or write one yourself and ask for a yes.
- Extras that creep in: log each extra as a change request, estimate the hours and let the client decide.
Finish with a note about hours
On every closed project, write two lines: how many hours you estimated and how many you used, with the reason for any gap. After ten projects, those lines are the best pricing guide your studio will ever own.